Major Projects 2016-2017

At St Mary’s we do have a vision for a future where our church is central and relevant to modern village life, where we attract newcomers and are welcoming to all who visit , where we further develop our use of technology within the church to enhance the experience of our congregation and our visitors.  We recognise the need for change in order to progress our mission and are keen to be able to start on exciting new projects.

But, before we can do that, we have a number of large and necessary maintenance projects that urgently need our attention.
The roof to the chancel & organ chamber – completed Dec-2016
The stonework on and around the tower –  starting Aug-2017
The exterior wall and roof of the vestry
Renovation of the historic organ

As with any large project, the costs are considerable.  Our congregation already contribute to the full, in order just to meet the costs of running the building and the ministry share which we pay to the Diocese.  So part of the process for any new project must be applications for grants and other outside sources of funding.  Although we have several large projects, they are very different and, hopefully, will attract different sources of funding.

This page was created in May 2016 and is being updated regularly as the projects progress.  We would appreciate your prayers as we work on these projects. Our Restoration Appeal was launched on September 10th 2016 and is intended to cover all of these projects.  For updates on the Appeal and on the different ways that you can give, there is a separate webpage here.

THE CHANCEL ROOF (and surrounding area) – COMPLETED DEC-2016
The church building is inspected by the Church Architect every five years and he advises on works that are needed in his Quinquennial report.  At St Mary’s the last inspection took place in November 2014.  The chancel roof, which we know has been prone to occasional leaks, and the north transept (organ chamber) roof are both mentioned in the 2009 and 2014 quinquennial reports as needing repair.  The chancel roof itself is the responsibility of the church commissioners, so we did not have to raise funds for that repair.  However, the chancel roof is attached to the north transept roof (over the organ chamber) so it was sensible to have both roofs repaired at the same time.
Our first grant application (Feb-2016) to LPOW Roof Grants was not successful.
We had permission from the Diocese (List B Authorisation) to complete this work and had a bat survey done.   The roofwork had to be completed in the period September– March to avoid disturbing any bats as far as possible. A grant of £1,000 towards this project was received from All Churches Trust (September 2016).

Monday 19th September 2016 – the scaffolding started to go up
Monday 17th October 2016 – work on the roof started in earnest with lead stripping
chancel roof  img_1075    img_1091

Tuesday 1st November 2016 – after recasting of some lead and repairs to some timbers, work started on installation of the new roof. Here are a few unusual views of/from the chancel roof

Monday 28th November 2016 – the lead work is complete and the stonemasons are at work making some repairs and repointing.
Monday 5th December 2016 – The roof is fixed, the covers are off and the scaffolding has started to come down. Now that our chancel is weather-proof, on we can move to planning and fund-raising for the next big project. Thanks to all who have supported us so far with sponsorship, events, grants, donations….
roof.jpg      img_1171  roof-completed

 

STONEWORK (especially in high areas) – STARTING AUGUST 2017
An urgent item highlighted in the Architect’s 2014 Quinquennial report was to check and repoint the clerestory parapet (shown below).
clerestory parapet               tower-parapet
Although not a huge job in itself, it seemed sensible to group this urgent item with other stonework requiring attention.  Such as :- rebed / repoint spire base; decorate clerestory rainwater goods; Tower parapet pointing ; lower level selective repointing.  Much of the area needing attention is not easily accessible and would require scaffolding or similar.
Sub –Project :  THE CLOCK
Whilst there is scaffolding in place around the tower, it would be sensible to carryout repairs to the external parts of the clock either as part of the overall project or as a separate project.
 In the last week of July-2017 we were awarded a grant of £40,000 (the maximum available) from the Amey Community Fund. This money supplements the ongoing fund-raising successes of the restoration appeal and allows us to start the essential maintenance work on the tower and repairs to the clock.
The work will start in August and should be completed by the end of November 2017. 
We already have a List B permission from the Diocese in place to cover this work.

THE ORGAN

Our organ is a Nicholson and Lord, 3 manual and pedal board, tracker action instrument which is not only rare but is over 100 years old.

For some time now, the organ has been having problems which cannot be rectified without a complete overhaul and re-built.  At the moment the organ is covered for protection whilst the work on the roof above is completed
organ playing

We already have one cost-estimate of around £85,000 and are in the process of getting some more cost estimates for this work. It has been proving quite difficult to get a second or third cost estimate.  However, we are now hopeful of getting these in the New Year (2017).

At the same time, we are looking at potential sources of funding for this project and plan to submit a faculty application for permission to do the work.   The organ is an important part of our history at St Mary’s and, as such, will hopefully be able to attract specific grants and other funding on the basis of heritage and music.

VESTRY ROOF & WALL

The vestry roof is in need of a more permanent cover and the exterior walls need repair.

Although technically less urgent we are aware that this area is unsightly and does need attention at some point.  This project is under discussion with the church architect and was mentioned in the Quinquennial report of 2014 for action within 5 years (now only 3 years are remaining).

vestry